If you’re dreaming of turning your backyard into a private escape, one of the first questions you’ll likely have is how long the process actually takes. Building a custom swimming pool is exciting, but it’s not an overnight project. From design to the first swim, there are several phases involved, each with its own timeline. So how long does it really take to build a custom pool in Rockwall? Here’s what you need to know.
Average Timeline for Custom Pool Construction in Texas
On average, building a custom inground pool takes about 8 to 12 weeks from start to finish. However, the timeline can vary depending on your pool’s complexity, weather conditions, permitting delays, and your builder’s schedule. Some pools are completed in as little as 6 weeks, while more elaborate designs can take 3 months or longer.
1. Design and Planning
Timeframe: 1 to 3 weeks
The process starts with a consultation to talk through your vision, backyard layout, and budget. After that, the design team creates custom plans and 3D renderings for approval. This phase also includes choosing materials, features, and finishes.
2. Permitting and Approvals
Timeframe: 1 to 4 weeks
Once the design is finalized, the next step is securing permits from your city or county. Depending on where you live, this part of the process can be quick or take several weeks. Your pool builder will handle this paperwork, but permit approvals are often outside their control.
3. Excavation
Timeframe: 1 to 3 days
After permits are approved, construction begins. Excavation involves digging the hole for your pool and preparing the ground. It’s a fast process, but it will temporarily turn your yard into a work zone.
4. Steel, Plumbing, and Electrical
Timeframe: 1 to 2 weeks
Next comes installing the steel framework, plumbing lines, and electrical systems. This stage creates the skeleton of your pool and sets the groundwork for everything that follows.
5. Shotcrete or Gunite Application
Timeframe: 1 week plus curing
Once the framework is ready, your builder applies the concrete shell of your pool using shotcrete or gunite. After it’s applied, the concrete must cure for several days to a week to ensure long term durability.
6. Tile, Coping, and Decking
Timeframe: 1 to 3 weeks
This is where your pool starts looking like the real deal. Tile and coping are added around the pool edge, and the surrounding deck or patio is constructed. The timeline depends on the materials you choose and how complex the design is.
7. Interior Finish and Start Up
Timeframe: 3 to 7 days
The final step is applying the interior finish such as plaster or pebble and filling the pool with water. After that, the start up process begins, which includes balancing chemicals and making sure all equipment runs smoothly.
Other Factors That Can Affect the Timeline
While the steps above are typical, a few things can cause delays. These include bad weather, changes to the design mid project, permitting holdups, or high demand during peak season. Working with an experienced builder helps keep the process on track and your project moving forward.
Plan Ahead to Swim on Schedule
If you’re hoping to enjoy your pool by summer, it’s best to start planning several months in advance. A little preparation goes a long way toward avoiding delays and making sure you get the pool you’ve been dreaming about.